Dumping fill.
June 3, 1996
It finally stopped raining long enough to back-fill around
the foundation. I ordered some gravel and fill from a trucking
company. The excavator then arrived in the early evening and
back-filled the perimeter walls with a thick layer of gravel on
the drain tile followed with dirt fill left over from excavating
the foundation. The inside of the foundation will be leveled off
with a lime waste fill in preparation for the concrete flat work.
This interior fill will be positioned using a skid loader,
however I have a cold storage room which is too small for a skid
loader so I had Chris dump fill into
this room with his Excavator. Of course I will
still have to level this room by hand.