December 4, 1994: Reviewed Log Home Companies.
July 25, 1995: Wilderness Log Homes Selected. Down payment sent.
January 23, 1996: Decided to General Contract myself and started list of sub-contractors.
April 2, 1996: We start clearing the property.
April 6 - 27, 1996: The rest of the family helps clear the property.
April 29, 1996: Official Ground breaking, grab your shovel (snow shovel that is).
May 1, 1996: The bank gives us money (to bad they want it back someday).
May 3, 1996: We actually break ground.
May 6, 1996: The storage trailer arrives, what a monster!
May 6, 1996: The Concrete Footers are poured.
May 14, 1996: Wilderness Log Home lumber trucks arrive.
May 17, 1996: Putting up the concrete wall forms.
May 21, 1996: Concrete Walls poured.
May 30, 1996: Installing drain tile.
June 3, 1996: Back-filling with the excavator.
June 5, 1996: Putting fill inside foundation. (See the flying skid loader!)
June 6-7, 1996: Rough in foundation plumbing.
June 14, 1996: Pouring concrete flatwork.
June 18, 1996: HURD Windows Delivered, nothing broken.
June 24, 1996: Builders begin framing.
June 26, 1996: We have walls. (Our first meal in the new Kitchen).
June 28, 1996: Flooring built in preparation for suspended concrete ceiling.
July 8, 1996: Great room beams are craned into place.
July 9, 1996: Work begins on second floor.
July 11, 1996: Suspended concrete ceiling poured.
July 15, 1996: Rafters and dormers.
July 16, 1996: Logs delivered!!!
July 18, 1996: Great Room Rafters.
July 21, 1996: Cleaning mold, mud & mildew from front porch logs. Its a dirty job but ...
July 24, 1996: Chimney chase framed up.
July 26, 1996: Roof sheeting and front porch completed.
August 1, 1996: Rear deck and screened-in porch framed.
August 8, 1996: Roof shingling begins.
August 13, 1996: Fireplace insert installed.
August 17, 1996: Windows installed and we got to help.
August 21, 1996: We start to log (see it really is a LOG home).
August 22, 1996: Water hookup complete.
August 23, 1996: Backside of house logged.
August 24, 1996: Quality checking construction and building retaining wall.
August 30, 1996: South side logged and starting the front side.
September 1, 1996: Scheduled moving day (we couldn't move yet so we had a deck party instead).
September 2, 1996: North side and garage logging.
September 10, 1996: Ductwork finished, furnace installed and plumbers start rough-in.
September 11, 1996: Power company connects the electrical and gas.
September 12, 1996: Do-it-your-selfers start installing the electrical wiring.
September 13, 1996: Exterior Logging completed! (Best picture)
September 17, 1996 Installing communications wiring (learn about "Smurf" tubing).
September 21, 1996 Friends help with garage doors.
September 26, 1996 Inside log stairs.
September 29, 1996 Finally sold the old house, but we had to be creative to do it!
October 2, 1996 Finished deck and 4 season room.
October 5-6, 1996 Friends help insulate and finish electrical wiring.
October 8, 1996 Knotty pine ceilings.
October 11, 1996 Started inside stair railings.
October 16, 1996 Septic tank and field
October 16-18, 1996 Dry-wallers hang sheetrock.
October 28, 1996 Gas hooked up and furnace started.
October 29, 1996 Dry-wallers start taping and muding.
November 1, 1996 Close on old house and extend construction loan.
November 9, 1996 Moving Day! At least for our furniture and stuff
November 15, 1996 Installed bath vinyl, toilet, showers and laundry sink.
November 16, 1996 We move in!!!!!! Bedrooms in the basement.
November 23, 1996 Upstairs bedrooms' logged.
November 28, 1996 Lots of painting and atic stairs installed.
December 3, 1996 Wood floors installed upstair's bedrooms (we move out of the basement).
December 9, 1996 Installed 6 panel pine doors in bedrooms.
December 10, 1996 Stove, microwave and dishwasher delivered.
December 11, 1996 Bathroom vanities installed.
December 14, 1996 Some kitchen cabinets set. Margaret has first dinner party.
Decmeber 18, 1996 Deer in the backyard for breakfeast.
December 25, 1996 It's a white Christmas in our new log home!